Contact info

Project Location Details

The Upper Sanigad Hydro-electric Project (USGHP) is a run-of-the-river type scheme situated in the picturesque locales of Kaphalseri and Pipalkot Village Development Committees (VDCs) within the Bajhang district of the Seti zone, Far Western Region of Nepal.

River System:

Sanigad River serves as a major tributary of the Kalanga River, which in turn, is a significant tributary of the Seti River.

Transmission Infrastructure:

In anticipation of multiple upcoming hydropower projects in the Seti basin, Nepal Electricity Authority (NEA) has undertaken the construction of a 132kV transmission line connecting Chamelia and other mega projects. This infrastructure will facilitate the evacuation of power generated by USGHP to the NEA substation located at Balanch in Darchula district, approximately 20km away from the proposed powerhouse of the project.

Access Roads:

A gravel road running along the left bank of the Sanigad River provides operational access to the proposed powerhouse and Kaphalseri. Additionally, a 10km long project access road is slated for construction to reach the headworks at Mallo Bagad Village and the surge shaft of the project. Seasonal crossings will also be developed across the Sanigad River at Kaphalseri to facilitate access to the headworks.

Project Implementation

The contractors for the completion of the project element in the realization of the project are as follow

S.N.Contractor titleContractor
1Civil ConstructionSunam Infrastructure Nirman Private Limited
2Hydro-Mechanical worksSunam Infrastructure Nirman Private Limited
3Electro-Mechanical worksAndritz Hydro Private Limited
4Transmission LineMudhbary and Joshi Construction Private Limited
5Design and construction supervisonAngel Engineering Consultancy Private Limited

 

Apart from that the company has employed Team of engineers, Technical and non-technical staffs from the early stage of the construction activities. The active participation of the teams especially in the electromechanical installation work and Transmission line installation works has gained the valuable experience for years to come for the operation and maintenance of the project during the generation stage.